First shipment of timber has arrived!

First shipment

The first container of timber has arrived in Lyttelton and is clearing customs as I write.

This container is planks for the decking (mostly the platforms). This shipment contains around 844 linear metres of 4.2-metre-long planking.

Timing of road closure

Today, we caught up with the project manager for HEB. The traffic management plan has been approved and they’re currently waiting for ECan to approve the construction management plan. Depending on how long that takes, it’s likely that closure of the road to vehicles will begin around 24 to 26 August, followed by site set-up in early September.

We’ll keep you posted!

To see the design of the new jetty, including the landward and seaward end platforms, see the Project page.